top of page

'The Bloc' Condos

We build beautiful, lasting brick condos with modern style.

2160 Grant Ave, Port Coquitlam

This project was subcontracted to our company by Detail Masonry. Our scope included installing Charcoal Vesta brick while coordinating with site conditions, maintaining safe and efficient access, and helping keep the project on schedule through the winter months.

We erected and managed our own scaffold staging to support the masonry work. The access system used A-frame scaffolding with outriggers, configured to provide stable working platforms across the building.

To support production, we established loading bays and used telehandlers to move materials to the work areas. This approach helped maintain a consistent supply of brick and other materials while limiting interruptions to the crew.

During construction, we encountered areas where the building framing was out of plumb. These conditions required careful, extensive layout to keep the completed brickwork plumb while coordinating with the building’s existing geometry.

Particular attention was given to maintaining open wall cavities. In some locations, brick had to be cut by as much as ½ inch to preserve the required cavity space. This work required ongoing measurement and adjustment so the masonry could accommodate framing irregularities without compromising the cavity.

The project proceeded during the winter months. To maintain production and support the project schedule, work areas were protected with tarpaulins and heated with propane heaters. These measures allowed the crew to continue working through cold-weather conditions and helped keep the masonry work moving.

All brickwork was completed in accordance with BC Masonry standards. The work required careful layout, consistent attention to plumb, and coordination with varying site conditions.

Project Summary

This project demonstrates our ability to manage masonry installation from access and material handling through to detailed field coordination. Despite out-of-plumb framing and winter conditions, our crew maintained the brickwork’s alignment, preserved the wall cavities, and kept the work progressing toward the project schedule.

Project summary

Project name

'The Bloc' Condos

Budget

Subcontracted

Scope

Brick Cladding installation

Duration

6 Weeks

Photos

bottom of page